Biogas plant and biomethane plant I and II Satuelle
Biogas plant and biomethane plant I and II Satuelle
Biogas plant and biomethane plant I and II Satuelle
We were responsible for the entire planning, plant construction, gas upgrading and operation of the biogas upgrading plant in 2013 and 2014 until the plant was sold.
Biogas plant and biomethane plant I and II Satuelle
Technical details:
2 biogas plants with 1400 Nm3/h biogas each
Planning, plant construction, biogas-biomethane upgrading and operation (until 2016) by revis bioenergy
Processing of approx. 55,000 tons of silage per year
Capacity of the silo facility approx. 15,000m2 sufficient for approx. 48,000 t (85% of the annual requirement)
Biomass approx. 55,000 tons of renewable raw materials (maize, millet, grass, GPS) from approx. 10 suppliers